System 300 / for Slab Lane
Page: 119-07
Rail flange Skl 15 Installation instructions Correct The correct installation clamping position is achieved when the intermediate loop touches the rib of angular guide plate by tightening the sleeper screw. (max. Permissible air gap: 0.5 mm). A tightening torque of approx. ≤ 200 Nm is required.
Wrong Intermediate loop does not rest, air gap is too large. Desired clamping force is not reached!
installed
pre-installed
8 7 6 5 4 3 2 1 Pos.
1 1 1 2 2 2 2 1 Number/Support point
Intermediate level Base plate Intermediate level Plastic dowel Angular guide plate Rail clamps Sleeper screws with track Rail Designation
Zwp 104 NT Grp 21 Zw 692 Sdü 25 Wfp 15a Skl 15 Ss 36 with Uls 7 60E2 Brief description
Without scale/schematic diagram
Date of issue 08/10